Yellowhead Trail Upgrades

Lots utility/first-call flags up on the 107 St/Yellowhead intersection. Have to think construction will be starting soon there.
 
Global News shot of 127 Street:
1744034480658.jpeg
1744034480658.jpeg
 
Regarding the segment from St. Albert Trail to 97 Street:

Construction Update - Spring 2025​

Construction of the project continues into spring 2025 with the following work within the project limits:

  • Pile installation for the new interchanges at 127 Street and 121 Street
  • Installation of underground utilities
  • Roadway reconstruction
Two lanes in each direction will remain open, with left turns at Yellowhead Trail and 127 Street prohibited.

Please continue to watch for detours and slow down to ensure the safety of pedestrians, commuters and our construction team.