Valley Line LRT | TransEd/Marigold | City of Edmonton

Just going by the Q1 2024 progress update saying construction progress is only 16.2% after over 27 months of construction, that does track that they're definitely running severely behind if this is supposed to be five years of construction. Between Q1 2023 and Q1 2024, they only made 10.2% construction progress.

Pretty ugly stuff to read when typically this is the time where most construction progress is made (mid project) as you're fully staffed up, pre-lim work largely done, but before the slow fine detail stuff comes in later.
16.2% was only up until March 2024, so that would be only ~22 months as construction didn’t “officially” start until end of may 2022. And yes I don’t count “pre construction” as actual construction.

Maybe I’m wrong but I still don’t see how it’s 2 years behind schedule, but I guess I’ll wait to see the city officially come out and say something concrete.
 
Now that the difficult infrastructure is mostly built, I expect any future delays to be caused by underpaying workers, leading to perceived (but not real) worker shortages.
 
Now that the difficult infrastructure is mostly built, I expect any future delays to be caused by underpaying workers, leading to perceived (but not real) worker shortages.
I would believe that MIP has been trying to dramatically cut labour costs to maintain budget on this given inflationary pressures. How much evening/night work has been getting done on this job? Most VLW sites I see have no movement on evenings and never on Sundays. Meanwhile felt like TransEd was running night shift crews constantly, especially on the tunnel.

I also wonder if they wound up feeling a labour pinch with Standard General's labour force being so dedicated to the Yellowhead project, which I've heard really went off the rails and was supposed to have been completed last fall that they're still trying to wrap up now, even with getting an extra basically month and change of construction season with the killer fall we had.
 
I would believe that MIP has been trying to dramatically cut labour costs to maintain budget on this given inflationary pressures. How much evening/night work has been getting done on this job? Most VLW sites I see have no movement on evenings and never on Sundays. Meanwhile felt like TransEd was running night shift crews constantly, especially on the tunnel.

I also wonder if they wound up feeling a labour pinch with Standard General's labour force being so dedicated to the Yellowhead project, which I've heard really went off the rails and was supposed to have been completed last fall that they're still trying to wrap up now, even with getting an extra basically month and change of construction season with the killer fall we had.
They’ve been working 24/7 with the gantry crane for about the last 3 months.
 
I seem to recall the SE line was "on time" for the first few years until it suddenly wasn't, even to the point where noone believed them. I don't like Gunther either, but I wouldn't be surprised if Marigold doesn't admit to delays until its forced to, why would they? The labour market, cost control to mitigate inflation, and supply chain issues have been rampant for everyone the last two years, why would this be any different.
 
I seem to recall the SE line was "on time" for the first few years until it suddenly wasn't, even to the point where noone believed them. I don't like Gunther either, but I wouldn't be surprised if Marigold doesn't admit to delays until its forced to, why would they? The labour market, cost control to mitigate inflation, and supply chain issues have been rampant for everyone the last two years, why would this be any different.
That is not how I remember it. To a casual observer just a couple of years into construction I was concerned over the lack of progress.
 
That is not how I remember it. To a casual observer just a couple of years into construction I was concerned over the lack of progress.
That is what I meant by "noone believed them", I seem to recall TransEd saying things were "on time" for longer than was credible. Avoiding admitting delays until the last possible moment seems to be the usual MO for companies. So if there are delays on the West line, I'm skeptical that Marigold would be quick to admit it.
 
That is what I meant by "noone believed them", I seem to recall TransEd saying things were "on time" for longer than was credible. Avoiding admitting delays until the last possible moment seems to be the usual MO for companies. So if there are delays on the West line, I'm skeptical that Marigold would be quick to admit it.
And TransEd only ever blamed the concrete in the river for their delays, at least until they no longer could.
 
It would definitely be unfortunate if the entire project is delayed. That's where it's too bad that they couldn't open up in phases. Starting from downtown they could open up til 124 street, then next phase 6 months later to Stoney Plain Road, 6 more months to meadowlark mall, and final phase anther 6 months to Lewis Farm. I know they can't do that most likely, but assuming problems are further west, it gives them more time and it at least makes it feel like there isn't as much of a delay.
 
It would definitely be unfortunate if the entire project is delayed. That's where it's too bad that they couldn't open up in phases. Starting from downtown they could open up til 124 street, then next phase 6 months later to Stoney Plain Road, 6 more months to meadowlark mall, and final phase anther 6 months to Lewis Farm. I know they can't do that most likely, but assuming problems are further west, it gives them more time and it at least makes it feel like there isn't as much of a delay.

I doubt they could it in phases because each phase gets more expensive, and takes more time. I'd rather they do it all in one fell swoop.
I just wish they could have included an extension to the Lewis Farms recreation centre.
 
Last edited:
Is there a repository of older books over time? I found one on google from 2021, and while there weren't too many differences, it'd still be nice to see how it changes over time as design work progresses.
No, the city usually doesn’t archive most things. For example the never archive their mid season and year end construction updates, for some reason?
 