16.2% was only up until March 2024, so that would be only ~22 months as construction didn’t “officially” start until end of may 2022. And yes I don’t count “pre construction” as actual construction.Just going by the Q1 2024 progress update saying construction progress is only 16.2% after over 27 months of construction, that does track that they're definitely running severely behind if this is supposed to be five years of construction. Between Q1 2023 and Q1 2024, they only made 10.2% construction progress.
Pretty ugly stuff to read when typically this is the time where most construction progress is made (mid project) as you're fully staffed up, pre-lim work largely done, but before the slow fine detail stuff comes in later.
Maybe I’m wrong but I still don’t see how it’s 2 years behind schedule, but I guess I’ll wait to see the city officially come out and say something concrete.