Seems to be going at a pretty good pace to me. They seem to be on site every day of the week. Ground level always seems to take the longest, as well as the rest of the underground floors.
3-4 weeks per level below grade (in this case 5) and then 1 floor a week once they get past the podium, following a standard schedule. You're totally right, getting to grade always seems to take forever. I think most recently the View in Grandin was similar. the hole was there forever, then they hit grade, then POOF a tower appeared.
 