Warehouse District Park

Screenshot 2024-02-01 at 2.25.18 PM.png
 
Leaving what?

You generally do not tender something very far in advance as price escalation will leave you high and dry. A 30-60 day tender/RFI period, 30 day evaluation and award still provides time to mobilize and start construction for this season.
 
Leaving what?

You generally do not tender something very far in advance as price escalation will leave you high and dry. A 30-60 day tender/RFI period, 30 day evaluation and award still provides time to mobilize and start construction for this season.
But they aren’t awarding a contract they are asking for qualifications. How long does that process take ?
 
Feb 23 this RFQ closes. Say a month or so to evaluate and short-list and then a 30 day tender or so, with an award and mobilization mid-May?
 
I can't imagine once they start this that it will take too long to finish right? Tearing out old parking lots, doing some utilities work, and landscaping shouldn't be too long of a construction period.
 
IMO they are definitely going to miss 2025 in terms of completion... 2026 is the new agenda time-frame.
 