Valley Line LRT | TransEd/Marigold | City of Edmonton

Can they be, sure, should they be if other options are available, maybe not where possible.

But like anything, risk can be mitigated at a cost and through design if a need is there.

You do not *typically* see residential/commercial transformers or switching cubicles incorporated into, versus outside of buildings by way of PMTs or vaults.
 
No rest for the Gantry crane, one new guideway section built west of 178 Street.

Also, more track slabs built west of 178 Street. More concrete curbs poured around SPR/102 Avenue to west of 142 Street. Curbs built on south side of SPR west of 124 Street.
 
Last edited:
Pretty good ridership in the VLSE to Folk Fest from what I saw. I did see one train in particular that had a lot of standees, although I wouldn't necessarily call the cars full. Service was also only every 15 minutes at the time. All trains were 2 cars, as opposed to the usual single and double car mix. Service did increase to 10 minutes at 14:30, but I wasn't around at that time so I don't know if was busier at that point or not. Davies park and ride had more cars than a weekday, but it was no where near capacity. Half the lot was still empty at 13:00ish.
 
updates:
IMG_0837.jpeg


IMG_0838.jpeg

IMG_0841.jpeg

IMG_0843.jpeg

IMG_0846.jpeg

IMG_0847.jpeg

IMG_0849.jpeg

IMG_0851.jpeg

IMG_0854.jpeg
 
Just a question, are the orange crosswalks going to be built at every intersection? Maybe key intersections, but I don’t think it’s necessary for crosswalks or ones for side roads.
 