Valley Line LRT | TransEd/Marigold | City of Edmonton

IMG_9286.jpeg

109st to 121 st should all be paved in the next few days
 
Some other observations (some reported earlier):
(1) The first rail crossing done at the west portion of 109 Street.
(2) Some sections of 104 Street eastbound completed.
(3) New sections of LRT crossings (112 and 116 Street eastbound) making progress.
(4) More digging at the median west of 124 Street.
(5) More trackbeds poured in Glenora, also east of 142 Street station.
(6) Westbound sections of SPR paved between 145 and 156 Street.
(7) Trackbed poured at 149 Street.
(8) Trackbed poured at 95 Ave/156 Street.
(9) Median work at 156 Street/Meadowlark Road.
(10) Last section of flyover being assembled west of 178 Street.
 
I stand corrected, looks like 87 Avenue needs reconstruction on the north side west of 178 Street, WEM, and Misericordia. At least this construction is not next to LRT.
 