Aldritt has always been quite conservative. But I felt this was a bold and welcome move by the younger Aldritt members. However deep down this particular projects will not get built, At least as we see it. a much smaller project may come. Is there is some politics at play probably. The supply chain is not a factor as much anymore. We factor in long lead time for products. And the big lead times seem to be on the electrical side now. Financing will hold some projects up but not this one. If it didn't happen earlier it will not happen. What may kick this further down the road is the labour issues. This last few months has shown me that that is the number one concern.
Looking at next year there is a phenomenal amount of RFPs. So the will to build is there. JUST maybe not this one.