northlands
Senior Member
Crane was supposed to have been installed in December.... then it was shoring wall failure, then too cold, then I guess they switched which contractor was doing the formwork and craning. Still moving ahead, just slowly.
I thought the same for awhile, but I can see the 95th st HAT from my balcony, and it was pretty lit up and occupied looking the other day.I love the fact that Cidex continues to build but I have to ask, including Calgary, I never see many lights on in any of their buildings. Anyone else notice this?
Is there something off with how they build? I've never actually toured a cidex building so I don't have a good perspective.
Guess so: https://new-firmus.com/Sorry...."New-Firmus" is the GC?
Sounds like they are the concrete formworker. Not sure who GC is, maybe in-house by Cidex?Sorry...."New-Firmus" is the GC?
2 Calgary based firms.Yeah CIDEX is in-house GC'ing this project, New Firmus is the formwork/craning.