by Chris Vazquez, on Flickr
This last one is a good reminder that this tower will still be quite large. Still taller than manulife by a bit, which you can currently see from the west of the city from way way out, as well as the south. Considering where this is being built, you will see it from the west without doubt.
 
Last edited:
Anyone been able to get the updated renders from ONE Properties? I tried emailing, but no joy. Haha. Seems the only shots are the photos of photos from their proposal a while back.

Looks like that corner is almost ready to get going now.
 
As per GreenSPACE on C2E:

Arena District Local Advisory Committee Meeting last evening. Some updated completion times:

- Stantec Tower - Late 2018
- Stantec Podium - Early 2019
- JW Tower - Early 2019
- Legends Residences - Early 2019
- Allard Parkade - Early 2019
- Greyhound Podium - Mid 2019

- Stantec Tower Residential - Late 2019
- Ice Plaza - Late 2019. Will include public skating rink in winter and performance stage in summer
- Greyhound Tower - Fall 2020
- Baccarat will come down sometime this year.
- 103 Street - parkade will be at grade by November, work to start on street.
 
Update as per IanO on C2E:


Ice District

Subject to Change

Stantec Tower: 1st Occupancy Date: Late 2018
Stantec Office Podium: 1st Occupancy Date: Late 2018
JW Marriott: 1st Occupancy Date: Early 2019
Legends Private Residences 1st Occupancy Date: Early 2019
Stantec Podium Retail Shops 1st Occupancy Date: Early 2019
Greyhound Site Podium 1st Occupancy Date: Mid 2019
Stantec Tower Residences 1st Occupancy Date: Late 2019
ICE Plaza 1st Occupancy Date: Late 2019
Greyhound Tower Residences 1st Occupancy Date: Fall 2020


Grocery Store Greyhound Site
Cinema Greyhound Site
Pharmacy Stantec Podium
Restaurants Stantec, Hotel, Edmonton Tower & Greyhound Site
Sports Bar Grey hound Site
Day Care Edmonton Tower
Retail Shops Greyhound Site, JW Marriott & Stantec Retail Podium
Hotel JW Marriott
Spa JW Marriott
Fitness Centre JW Marriott
Skating Rink ICE Plaza
Performance Stage ICE Plaza
Residences Legends, Stantec & Greyhound Site
Parkade Under ICE Plaza, JW Marriott & Greyhound Site
Plaza In the center of it all
 

Back
Top