Looks like they will be splitting up the main floor into 4 CRUs with large units at the back (entrance on Calgary trail) and in the basement. Possible closure of the alley on the west side of the building for a patio as well, which would be great (one less conflict point between pedestrians and vehicles!)


Not sure where Daily Hive got this brochure from though, not seeing it anywhere else online.

The contractor for this one is looking at starting in May/June.
 
BP:

2025-07-23
Commercial Final
To construct Exterior (facade updates) and Interior Alterations (demising walls, mechanical and electrical upgrades for future retail tenants) in an existing commercial building (A&N Exchange Building). NOTE: Signs and future tenant fit-ups require separate permits.
10405 - 82 AVENUE NW
$2,209,901
 
I went to look at some work in the building and one of the biggest issues is access to the lower level. There's no elevator and the stairs are wood construction or very narrow. Getting any large equipment onto that lower level is impossible at the moment, And cutting a hole in the main floor is limited by the open web joists and how they're suspended.

There was talk of going up, but reinforcing the structure would be very expensive.
 