Stop signs and grounding cables at 34 Ave today. WPE trailer sitting on the crossovers at MWTC. Wonder how many more things were done not according to plan? How long is this cable cleanup going to take? What other work is happening that they are scrambling like mad to complete while they can...
No train testing in Millwoods today. Grounding cables either side of the crossover south of the whitemud. Barricades and stop signs on both tracks . People messing around with what I assume the crossover signals - one in a box and two more on their knees messing with something on the rails
The issue is with the zig zag across 83 street as well as the removal of the traffic circle. I almost think they should have tried to route southbound traffic around the west side of the mall as you don't have to cross the tracks twice, but most people don't know that trick.
Trains creating quite the traffic gong show this afternoon around Bonnie Doon. 5+ minutes delay according to Google maps. There has to be a better way to coordinate traffic signals.
Fencing still around the Bonnie doon station. Also noticed that there is two of those light up no right...
Or the overhead catenary has issues and needs to be redone.... We've already seen some recent additions. Hoping not but with these clowns one never knows.
Looks like WPE has been doing some work on the overhead catenary at the 38 Ave station. There is some new shiny copper jumpers between the cables just south of the breaker on the southbound track.
I have zero faith this line will open this weekend. Maybe Sept 3 2024?
If they were opening this weekend we would have seen them running simulated service all week. There hasn't been a train down 83 street up to Strathern in how many months?
Weren't they originally saying they could replace the corroded cables in Millwoods while the line was running? We've been saying it for awhile now, but I don't think we can believe anything that the Transed Communication dept says.
How much testing can you do in such a short section of track though? Even training would be a bit of a challenge on such a small section of the line.
As mentioned earlier today the trailers are off the tracks finally at Bonnie doon. Also noticed that the concrete blocks they had installed at...
There is still concrete blocks across the tracks north of there though. It seems the blocks across the tracks at the top of Connors road are gone this morning, however there are still derails on both tracks there.
Some observations in Millwoods tonight:
I saw a train running! Passed a train coming down the hill towards 34 Ave on my way home
Digital message boards now rotate between Trains Running/No Right Turn on Red/Obey Traffic Signals
Additional lines painted on the far side of the tracks for east...