This article was posted in the Metro Line thread but has lots of good info regarding VL.
I get the VLW Director is being extra careful with his statements with no guarantees, but it sounds like their actual timelines are:
- 2026: all track laid
- 2027: wrapping up outstanding construction items and starting commissioning work
- 2028: more commissioning + testing
- 2029: open for public use
Which makes his statement that the project is "on-schedule" kind of ironic. Is the project really on schedule when you've adjusted the project schedule (including finish date) like four times now?